Adani Green Energy Limited (AGEL) has operationalized an aggregate 307.4 MW of renewable energy capacity at its mega Khavda Renewable Energy Park in Gujarat, further strengthening its leadership in India’s clean energy sector.
The newly commissioned projects include a mix of solar, wind, and hybrid power plants, developed through AGEL’s various step-down subsidiaries. With this commissioning, AGEL’s total operational renewable energy capacity has risen to 17,237.2 MW, one of the largest portfolios globally.
Following received of all regulatory and statutory approvals, the projects were declared operational at 7:47 AM on December 31, 2025. Power generation from these plants will begin on January 1, 2026.
What Was Commissioned at Khavda today
75 MW Solar
56.4 MW Wind
176 MW Hybrid (Solar + Wind)
Total: 307.4 MW
These projects were executed through AGEL’s step-down subsidiaries, ensuring faster deployment and optimized project management.
Read more about khavda Renewable Energy Park, Gujarat
Khavda Renewable Energy Park gujarat
Importance of Khavda Renewable Energy Park
The Khavda Renewable Energy Park in Gujarat is being developed as the world’s largest hybrid renewable energy project, combining solar and wind generation at scale.
Key advantages include:
- ⚡ Higher plant load factor through hybrid solar-wind configuration
- 🌱 Reduced carbon emissions and fossil fuel dependency
- 🔌 Improved grid reliability and round-the-clock renewable power
- 🇮🇳 Major contribution to India’s 500 GW non-fossil capacity target by 2030